Subestación Chincha Nueva de 220/60 kV y Subestación Nazca Nueva de 220/60 kV
State
Awarded
Modality
State Initiative Self-financed
Phase
Contractual Execution
Contractual modality
Concession contract
Competent Entity
MINISTRY OF ENERGY AND MINES
Sector
Energy
Portfolio
Electricity
Summary
Diseño, financiamiento, construcción, operación y mantenimiento de la Subestación Chincha Nueva de 220/60 kV con un CTI estimado de US$ 17.85 Millones, y la Subestación Nazca Nueva de 220/60 kV con CTI de US$ 15.72 Millones, ambos en el ámbito es el Dpto. de Ica.
Area of influence
ICA
Estimated Year Award
10/12/2020
Years of Contract
30
El proyecto seleccionado no posee Ficha General
Project Schedule
Announcement | Date |
---|---|
1. Call for and publication of Bases | Fri. - Sat. 04.18-17.20 |
3.5. Delivery of the Final Version of the Contract | 11.03.20 |
2. Tender Documents | |
2.1. Consultation to the Tender Documents | Until Fri. 07.31.20 |
2.2. Acquittal of consultations to the Tender Dcouments | Until Wed. 08.26.20 |
2.3. Publication of the Consolidated Tender Documents | Wed. 09.23.20 |
3. Contracts | |
3.1. Initial Version of Contracts | Fri. 04.17.20 |
3.2. Suggestions to the Initial Version of Contracts | Until Fri. 05.22.20 |
3.3. Delivery of the final version of Contracts | Wed. 09.23.20 |
3.4 Suggestions to the second version of Contracts | Up to 07.10.20 |
4. Qualification | |
4.1. Payment of the Participation Fee | Until Tue. 08.25.20 |
4.2. Submission of Qualification Request | Until Fri. 09.04.20 |
4.3. Corrections to comments | Until Fri. 09.11.20 |
4.4. Notice of Qualification | Fri. 09.18.20 |
4.5. Formation or modification of Consortia | Until Tue. 10.06.20 |
5. Submission of bids and Award | |
5.1. Submission of Envelopes No. 1 and No. 2 and Award (*) | 12.10.20 |
5.2. Corrections to comments in Envelope No. 1 | Up to 12.17.20 |
5.3. Opening of envelope No. 2 and Award | Up to 12.17.20 |
6. Process Closing Date | 03.10.21 |
(*)Should any of the documents in envelope No. 1 have to be corrected; activities 5.2 and 5.3 will be carried out. | |
(**)If it is a non-working day, it will be carried out on the following working day | |
Notice N°19 (03.01.21) |
Project Documents
Other Documents
Project Contacts
Name | Phone | |
---|---|---|
Aníbal del Aguila Acosta - Director de Proyecto | (51-1) 200-1200 anexo 1342 | adelaguila@proinversion.gob.pe |
Wendy J. Huambachano Neves - Asistente Administrativa | (51-1) 200-1200 anexo 1340 | whuambachano@proinversion.gob.pe |